Observing > Call For Proposals > NRAO Call for Proposals: Semester 2023A > VLBA, HSA, and GMVA Proposal Guide

VLBA, HSA, and GMVA Proposal Guide

Proposal submission information for the following three combinations of telescopes are detailed in individual sections below:

 

VLBA Proposals

The VLBA provides ultra-high angular resolution for astrophysical studies including:

  • Non-thermal continuum emission, including polarimetry, from active galactic nuclei (AGN), Galactic micro-quasars, pulsars, and other sources.
  • Maser emission lines of OH (1.7 and 6.0 GHz), CH3OH (6.7 and 12.2 GHz), H2O (22 GHz), SiO (43 and 86 GHz) and other molecules, and numerous thermal absorption lines, in a variety of Galactic and extragalactic circumstances.
  • Multiple-phase-center surveys across the primary beam.
  • Parallax and proper motion via differential astrometry of a variety of stars, star-forming regions, and nearby extragalactic objects, at accuracies as good as 10 microarcsec.
  • Absolute astrometry at accuracies of ~200 microarcsec to expand the International Celestial Reference Frame.

Overall information about the VLBA is available in the VLBA Observational Status Summary (OSS); specific sections relevant to various proposal types are linked below.

VLBA proposals must be prepared and submitted using the NRAO Proposal Submission Tool (PST), accessible via NRAO Interactive Services. Use of the PST requires registration by all proposers, including co-investigators, in the NRAO User Database.

Approximately 1000 hours of VLBA observing time are expected to be available for Open Skies in observing semester 2023A. In recent semesters, there has been less pressure in the GST range 0600 - 1800 hours as compared to 1800 - 0600 GST, and we expect this trend to continue.

Most approved VLBA observations are performed dynamically; for those dynamic observations, users must either submit their observing (.key) files (to vlbiobs@nrao.edu) before the beginning of the semester (February 01 or August 01 for A and B semesters, respectively), or contact the VLBA Scheduler (schedsoc@nrao.edu) before those dates to avoid a reduction in scheduling priority. Early submission of schedules maximizes the opportunity of dynamic observing and assists in the efficient scheduling of the VLBA.

VLBA Large and Filler Proposals

Large proposals (those which request 200 hours or more) are encouraged and welcome on the VLBA.  Such proposals should follow the Large Proposal Policy.  Large proposals which require multi-semester observations are often supported.

Filler proposals are also encouraged - these are scientifically useful programs that can be scheduled over a large range of GST, requiring fewer than eight VLBA stations, with low-frequency weather constraints, and short (2 - 6 hours) scheduling blocks.  Such projects can help to fill gaps in the dynamic observing schedule.  Filler proposals can be submitted as Regular proposals or even Large proposals (the Large proposal policy still applies); either Large or Regular filler proposals can be multi-semester proposals if scientifically justified.

Observing Capabilities for 2023A

For the 2023A semester the General Observing (GO) capabilities are given in the Offered VLBA Capabilities during the Next Semester section of the Observational Status Summary (OSS) and are summarized in the following table. Several additional capabilities are available to proposers through the Shared Risk Observing (SRO) and Resident Shared Risk Observing (RSRO) programs, as described below.

The GO capabilities being offered are:

CapabilityDescription
4096 Mbps recording
(requires DDC data system)
  • Available for the 6cm, 4cm, 1cm, 7mm, and 3mm receivers*
  • 1024 MHz polarization-summed bandwidth
  • Available for VLBA, global VLBI, VLBA+Y1, and HSA
  • We expect to be able to support this recording rate for most of the available open-skies observing time
*Note: 90cm, 50cm, 21/18cm, and 13cm bands require recording rates of 2048 Mbps or less due to their limited bandwidth
S/X Simultaneous Observations Up to 4096 Mbps recording rate (but slightly reduced sensitivity at both bands)
VLBA + Y1 Adds a single VLA antenna (Y1) to the VLBA to provide a short (~50 km) baseline to the VLBA Pt station
Multiple Phase Centers Up to 300 (or 150) phase centers at 4096 Mbps with a single correlator pass for dual polarization (or full polarization) products
Flexible Frequency Setup with the DDC data system
  • 1, 2, 4, or 8 data channels with bandwidths anywhere from 1 MHz to 128 MHz (all data channels must use the same bandwidth within an observing scan)
  • Data channels may be placed nearly anywhere in the IF
Flexible Spectral Resolution
  • Up to 4096 spectral channels per data channels for routine DiFX processing
  • Minimum spectral channel spacing of 2 Hz
Spectral Zooming
During correlation, allows the selection of a narrower frequency window to have a large number of spectral channels
Pulsar Modes
Binary gating, matched-filter gating, and pulsar binning correlation modes for pulsar observations

The VLBA operates two data systems, a Polyphase Filterbank (PFB), and a Digital Downconverter (DDC). These are described in detail in the Roach Digital Backend (RDBE) section of the VLBA OSS, which also includes suggestions for selecting the optimal observing system for various scientific goals. For the best continuum sensitivity (i.e. 4096 Mbps) at most receiver bands, or for the most flexible observing setups, the DDC is the better choice. For continuum observations using the 20cm or 13cm receiver bands, the PFB provides a setup using 2048 Mbps that can reduce the impact of prevalent radio-frequency interference (RFI).

Proposals requiring significant additional correlator resources, such as multiple phase centers per field or multiple pulsar phase bins, should consider mechanisms to support the correlation without adversely affecting the throughput of other projects. These should be entered in the technical justification section of the proposal.

VLBA Shared Risk Observing

The VLBA Shared Risk Observing (SRO) program allows observers access to capabilities that are essentially commissioned, but are not well tested. The following capability is offered under the SRO program during the 2023A semester:

  • Baseband Data Copy: Limited amounts of raw data recorded at each station can be copied to user-supplied media for correlation at a different location. See the VLBA OSS SRO section for more details.

VLBA Resident Shared Risk Observing

The VLBA Resident Shared Risk Observing (RSRO) program provides users with early access to new capabilities in exchange for a period of residency in Socorro to help commission those capabilities. For example, the phased-VLA system was developed through RSRO programs. Users are encouraged to conceive and propose innovative ideas for new VLBA capabilities. Some staff suggestions can be found at the VLBA RSRO program. For details about participating in the RSRO program, see the RSRO Considerations section in the Guide to Proposing for the VLBA.

Proposers should be aware that RSRO capabilities are generally not approved at priority A, owing to the level of risk associated with these observations.

 

High Sensitivity Array (HSA) Proposals

The HSA comprises the VLBA, phased VLA, GBT, and Effelsberg telescopes. Similar to the VLBA, all of the HSA stations can observe at 4096 Mbps (General Observing). The EVN Sensitivity Calculator can select 4096 Mbps for HSA sensitivity estimates. Details on the HSA telescopes are documented in the HSA section of the VLBA OSS, and special considerations on proposing and observing are listed in the HSA page of the Guide to Proposing for the VLBA.

VLBI observations combining the VLBA with any one or more of the other three HSA stations can be requested in a single HSA proposal. However, separate proposals must be submitted for any non-VLBI use of any requested telescopes.

HSA proposals must be prepared and submitted using the NRAO Proposal Submission Tool (PST), accessible via NRAO Interactive Services. Use of the PST requires registration by all proposers, including co-investigators, in the NRAO User Database. The inclusion of HSA stations should be quantitatively justified in the proposal. 

HSA Station Notes

• The phased Very Large Array (Y27) will be available for HSA observing in Semester 2023A, mostly in the B (~ Feb 2023 - May 2023) configuration, although a limited amount of time should be available in the A (~ July 2023) configuration, and during reconfiguration. Please note that high frequencies (at receiver bands 22 GHz and above) have better phasing in the more compact configurations (C and D).  High frequency phasing in the extended configurations in the summer can be quite difficult.

The Green Bank Telescope's (Gb) has significant scheduling constraints because of reduced open-skies time. Therefore, HSA proposals requesting Gb will likely have to be ranked at least in or near the top 10-15% of all AUI telescope proposals in order for GBT time to be approved. Proposers should clearly justify the need for the GBT in the text of the proposal. All proposers requesting the GBT should include any needed setup and overhead time in the total time request for their proposals. Additionally, proposers should be aware that long scheduling blocks (more than 6 hours) will be difficult to schedule owing to constraints coming from non-open skies time. Proposers are encouraged to make clear in the technical justification section any constraints about how observing time could be broken into smaller pieces without adversely affecting the proposed science; include information as relevant regarding maximum elapsed time of a split schedule and minimum scheduling block lengths.

Observations using the GBT 6-cm receiver as part of the HSA must be taken, correlated, and calibrated in full Stokes mode. Due to the large cross-talk between polarizations, only total intensity (Stokes I) data will be usable. 

• The Effelsberg (Eb) 100-m telescope supports both the PFB and DDC observing systems available on the VLBA. Consult this web page for more detailed information about the Eb HSA station.

 

Global 3mm VLBI Array (GMVA) Proposals

GMVA proposals submitted by the 2022 August 01 deadline will be considered for scheduling in 2023 Session I (May 04 - 09), or later sessions.

Complete information on the GMVA is available at the GMVA website. Ongoing special considerations are documented in the GMVA section of the VLBA OSS; new features and/or special cases are cited here.

As noted in the HSA section above, GBT time available for VLBI has been reduced due to its new partnership arrangements.

GMVA proposals must be prepared and submitted using the NRAO Proposal Submission Tool (PST), accessible via NRAO Interactive Services. Use of the PST requires registration by all proposers, including co-investigators, in the NRAO User Database. The inclusion of the GBT  in a GMVA proposal should be quantitatively justified. The KVN, or the Greenland Telescope (GLT) must be specified by entering  "KVN" or "GLT" as "Other" entries in the PST. Observations with VLBA telescopes at 7mm may be scheduled on the GMVA during pointing/calibration gaps on other GMVA telescopes; such 7mm observations can be proposed for.

The GMVA will record at the highest bit rate which instrumentation and resources permit. Currently all telescopes will record at 4096 Mbps.

New GMVA proposals requesting phased ALMA should not be submitted at the August 01 2022 (2023A semester) deadline.  Only proposals which were re-proposed at the Cycle 9 ALMA deadline - those that were approved for GMVA Session 2022/I but failed at ALMA - will be considered.
 

Documentation and Assistance

Detailed information about the VLBA instrument, its capabilities, observing strategies, proposal preparation and submission, and observation preparation, can be found in the VLBA Observational Status Summary, at the Guide to Proposing for the VLBA, and at the Observing with the VLBA web pages. Questions may also be directed to the NRAO Helpdesk.